Gldani, near the penitentiary institution, Gogiashvili street

Landslide

High

year 2021

recommendation

A protective wall should be arranged in the lane of the damaged and collapsed sections. Removal of detached and sliding soil mass and filling with ballast after wall construction by compaction of individual layers. The release and extension of the pipe provided for the previously existing drainage from the laid soil should also be conducted. Designing landslide prevention measures based on detailed geological studies is essential

year

Monitoring result

Status of the current year will be updated based on the information provided by the user.

We look forward to future updates and your involvement in monitoring the performance of existing data and recommendations. You can provide us by e-mail or through the contact form on this page, information about the geological process near your residence, current conditions, current or implemented measures with photo evidence.